Ask Kobayashi Steel Industries Ltd
“Fully customized”, “Quick delivery” and “Low cost”

TK construction method 002

On-site assembly of large-opening soundproof door

TK construction method 002

New construction method has made the on-site works more efficient

1. Improved efficiency in on-site works
Previously the door was delivered as a whole unit. In TK construction method, the door is divided into parts and delivered to the property, and therefore it significantly reduces overloads in carrying tasks.

2. Carry-in by parts
By dividing the door into several parts, they can be carried via the elevator. Stairs, crane, lifting machine, etc. are not required any longer.

3. On-site assembly
The door divided into parts can be reassembled easily. There are no need for welding, constructing, and finishing on site.

PAGE TOP